n Indonesia, many lands are still undocumented lands (i.e. traditional lands that are not registered with the Land Bureau).
Before applying for factory procedures, the most important thing is to ensure that the land use for factory construction meets Indonesia's industrial land requirements.
In addition to land requirements, the main process for building a factory outside an industrial park is as follows:
1. Company registration
Before building a factory in Indonesia, you must first complete company registration in Indonesia.
II. Environmental impact assessment technical approval
In Indonesia, technical approval is an important part of environmental management. There are three main types of technical approval: waste gas emission approval, wastewater emission approval, and toxic and hazardous waste treatment or utilization approval.
III. Environmental Impact Assessment Report
Outside the industrial park, technical approval must be obtained before an environmental impact assessment report can be processed.
IV. Building permit PBG
Before the factory officially starts construction, there is another important document that needs to be processed. That is PBG (building permit).
V. Production instructions for outside the industrial park
The production instructions for outside the industrial park is also one of the important documents. The specific requirements vary depending on the type of land where the factory is located.
VI. Activating the business license
After obtaining the environmental impact assessment report, you need to activate the business license.
VII. Construction qualification certificate SLF
SLF is a certification that must be obtained after a construction project is completed and fully put into use.
For more information on Southeast Asian investment, please consult PDAEXSEA professional consultants.